Colocating a single GPU server in 2026: what to settle before you sign

One 8-GPU server fits in one colocation cabinet, on air cooling, at many sites. What decides whether a site works is power per cabinet, how the two power feeds are sized, and whether the operator takes a single cabinet at all.

This note covers the current 8-GPU NVIDIA HGX B300 class of server. The same questions apply to any server drawing more than 10 kW.

How much power one server needs

Plan for 15 to 20 kW for a single 8-GPU server. The eight GPUs alone can draw up to 8.8 kW, and processors, memory, fans and networking add to that.

Two published builds on the same NVIDIA platform show the scale:

ServerSizeCoolingPower suppliesInputDepthWeight
Supermicro SYS-822GS-NB3RT8UAir6 × 6,600 W (3+3)200 to 240 V950 mm119 kg net
SuperX B3008UAir12 × 3,000 W (6+6)115 to 240 V, C19 cords930 mmNot published

SuperX lists each GPU at up to 1,100 W and each of the two processors at up to 350 W. The exact draw depends on the configuration you order, so ask your server vendor for the data sheet figure before you fix the power tier.

Size each power feed to carry the whole load

A cabinet with A and B feeds only protects you if either feed can run the server alone. Ask for the usable kW per feed after derating, not the breaker size.

Circuits are normally loaded to 80% for continuous use. On that basis, per feed:

CircuitUsable powerCarries 15 kW aloneCarries 20 kW alone
208 V three-phase, 60 Aabout 17.3 kWYesNo
208 V three-phase, 100 Aabout 28.8 kWYesYes
415 V three-phase, 60 Aabout 34.5 kWYesYes

These figures are Bargun's arithmetic (volts × amps × 1.73 × 0.8), not operator data. The step from 15 kW to 20 kW usually means a larger or higher-voltage circuit on both feeds, and that changes the monthly price. Decide the tier before you ask for quotes.

Cooling, depth and weight

Air cooling is enough for one server of this class, but 20 kW is at or near the published air-cooled limit at many sites. Of four US sites we read in November 2026, three publish a ceiling of 20 kW per cabinet and one publishes 35 kW.

Confirm three physical points in writing:

  • Depth. These servers are about 930 to 950 mm deep. Ask for the cabinet's usable depth with power strips and cabling in place.
  • Weight. One published build weighs 119 kg before rails and packaging. Ask for the cabinet and floor load limits, and how the operator lifts it into place.
  • Airflow. Ask what containment the site uses and whether blanking panels and a specific intake temperature are required.

Not every site takes one cabinet

Minimums are the quiet deal-breaker. Some operators sell single cabinets; others set a minimum number of cabinets or a minimum power commitment, and one of the four sites we read states a three-cabinet minimum. Ask this first, before anything else is priced.

Ask also for the minimum term, the deposit, how power is billed (flat or metered, and what an overage costs), and the earliest install date.

What to send us

Send five things to info@bargun.com or use the form below: the metro, the server model or its data sheet, the power tier (15 kW or 20 kW), the date you need it live, and your internet need (for example 100 Mbps or 1 Gbps). We reply within one business day, and we do not share your company's name with any operator without your approval.

Questions and answers

Can I colocate one GPU server without taking a cage?
Yes, at sites that sell single cabinets. Check the minimum first.

Do I need liquid cooling for one 8-GPU server?
Not for the air-cooled builds. Liquid cooling is for racks far denser than one server.

Is 208 V enough?
For a 15 kW tier, one 208 V three-phase 60 A circuit per feed carries the load. For 20 kW it does not; ask for 100 A at 208 V or a 415 V circuit.

What does the operator need from me to confirm a slot?
The server's data sheet (power, weight, depth, airflow), your power tier, and the install date.

Sources, all read on November 19, 2026: Supermicro SYS-822GS-NB3RT product page; SuperX B300 product page; operator pages for published power per cabinet and minimums: DataBank LGA3, Cologix NNJ3, Telehouse New York Teleport, Element Critical Chicago. Circuit figures are a Bargun calculation at 80% continuous load.

Start a project

Tell us the server, the power tier, and the date.

Send the basics and we'll come back with how we'd approach it, which sites fit, and a realistic timeline.

We reply within one business day.